Kingston Ocean Grove – Stage Update May 2020

Here’s what’s been happening in Kingston Ocean Grove & Kingston Coast

Coast Stage 1
– Weather permitting, forecasted completion of construction early June 2020
– Upon Statement of Compliance, soil testing and land valuations can be conducted
– Titles forecasted end July 2020

Coast Stage 2
– Anticipated commencement of construction works late June 2020
– Stage 2 administration and construction pre-commencement phase has been impacted by Covid-19 shutdowns, therefore forecasted construction completion is now end of4th quarter 2020
– Forecasted Titles 1st quarter 2021

“Parkside Bvd” Wetlands
– Wetland planting has commenced, and general garden bed and trees planting is scheduled from 1st June 2020
– Pergola construction is complete, with the timber boardwalk nearing completion
– Footpaths are substantially completed, with one remaining section of footpath to be completed by 5thJune following completion of the timber boardwalk
– Forecasted completion early June 2020
– Pending Council approvals, we hope to open this Reserve to the public from mid-June 2020

“Splendour Walk” Wetlands
– Targeted completion of civil earthworks clean-up, wetland shaping and topsoil is 3rdquarter 2020
– Weather permitting, general landscaping works to commence shortly after earthworks, towards the end of 3rdquarter 2020
– Due to the sensitivity of the Wetland plant species, final planting will likely be completed during 4th quarter 2020 in warmer weather.