Kingston Coast – Stage Update March 2020

Here’s what’s been happening in Kingston Ocean Grove & Kingston Coast

 

Coast Stage 1

  • All sewer and stormwater drainage is complete
  • Kerbing is complete
  • Water services & gas services installation is complete
  • Weather permitting, Electrical installation is set to commence shortly
  • Weather permitting, forecasted completion of construction end May 2020
  • Titles forecasted late 2nd Quarter

 

Coast Stage 2

  • Engineering plans are still with COGG & Barwon Water. We are actively following up on approvals, however, this is yet to be received.
  • Anticipated commence of construction works late April
  • Due to delays in plan approvals, forecasted construction completion is now 4th quarter 2020
  • Forecasted Titles 4th quarter 2020

 

“Parkside Bvd” Wetlands

  • Wetland shaping and topsoiling is complete
  • Some Wetland planting has commenced
  • Footpaths are underway and nearing completion
  • Weather permitting, forecasted completion early May 2020

 

“Splendour Walk” Wetlands

  • Targeted completion of civil earthworks clean-up, wetland shaping and topsoil in the 2nd quarter 2020
  • Weather permitting, general landscaping works to commence 2nd quarter 2020
  • Due to the sensitivity of the Wetland plant species, this will likely be completed during 4th quarter 2020 in warmer weather.